|
Saltend -
The Background to the Lock-out
Keith Gibson,
Lock-Out Committee (pc)
A couple of weeks ago
Redhalls (the company thrown off the site by Vivergo allegedly on 11th
March) had attempted to issue redundancies that would have breached
the NAECI agreement (National Agreement for the Engineering
Construction Industry). Approximately two weeks ago Redhall's had
attempted to issue redundancies on the basis of first in last out that
Redhall construction workers themselves had insisted upon, however,
Redhalls tried to implement this on the basis of first in last out of
all workers on site within their company (not first in last out on the
basis of this particular contract) - please note when the HR1 had
initially been applied for, Redhall's had started to transfer onto
Vivergo site their own permanent workforce within their own company
- in other words 'first in last out' on a Redhall basis would mean
that the original construction workers that were employed by Redhalls
to work on the bio fuels contract from its inception (i.e.: not
permanent workers within Redhalls) would be made redundant before the
permanent workforce that Redhalls (after the HR1 was applied for) were
just bringing onto the Vivergo site. This led to the strike
approximately two weeks ago.
Having secured
redundancy on a first in last out basis on the contract (after strike
action) and not company service a week later Redhalls were
allegedly removed from the Vivergo site on Friday 11th March,
however, Redhall employees were not informed. Over the weekend,
12th-13th March, rumours began to circulate amongst construction
workers that Redhalls had been removed off site. When
construction workers arrived for work on Monday 14th March Redhall
employees were refused access to the Vivergo site and a letter from
Redhalls informed them of a TUPE situation. To date the scaffolders
employed by Deborah Services Ltd and the electricians employed by SEC
Electrical have been laid off on pay awaiting a return to work on the
Vivergo site. The latter intimates that work on the Vivergo site is to
be reconvened. And yet, Redhall Solution Ltd employees including
Construction workers have been left in limbo - locked out from their
jobs with no reason given other than the company Redhalls are running
over budget. If Vivergo are to continue the bio fuels project (at
whatever point) this means the construction workers jobs are still
there and a TUPE situation is being blanked by a gap in time of
restarting this project on the mechanical side. It is this issue that
needs addressing.
Further - Officials
from GMB and UNITE attended a meeting with Redhalls on Thursday 17th
March. I was asked by the GMB to attend this meeting but Redhalls
would only speak directly with the Officials of both unions - this
meeting took place at the Village Hotel in Hessle and I along with the
shop stewards attended the Village Hotel speaking intermittently with
the Union Officials as the talks were in progress. Redhalls had
changed tack and were now offering a payment owing package while
allegedly agreeing a TUPE situation has arisen. Today on 21st March
the locked out construction workers rejected this pay package and
agreed on mass to escalate the fight to secure construction workers�
jobs and in defence of the NAECI agreement.
For construction
workers the scenario is - if they sign on JSA (Job Seekers Allowance)
they risk losing their TUPE rights. If they accept a payment owing
package this may breach their right to TUPE. In other words workers
face financial hardship due to the lock out. Construction workers have
not been laid off temporarily on pay like the scaffolders and
electricians and therefore overnight without any consultation have had
their jobs and pay withdrawn while it is plain that at some stage
Vivergo will be reconvening the same work on the bio fuels project.
For construction workers nationwide this poses the fact that TUPE is
being undermined by 'a gap in time' of resuming the bio fuel project
and it is this point that now faces all construction workers at
present or in the future. Put plainly the lockout can be re-construed
as the blacking of construction workers on mass.
Defend the
NAECI Agreement �don�t let the Bosses rip up the NAECI Agreement -
spread the word - send a delegation down from your site to the mass
protest - help build the campaign for a national walk out! If this
employer is allowed to lock-out 400 workers then your site could be
next -
DOWN TOOLS
IN SOLIDARITY!! |